BESIX completes its construction contract for Ectro’s Megafactory in Charleroi

BESIX and Galère have just completed Ectro’s new Megafactory in Charleroi (formerly Aerospacelab), a state-of-the-art industrial building spanning nearly 20,000 m² and combining distinctive architecture with highly specialised infrastructure.

Europe’s largest satellite factory

Recognisable by its ovoid shape, the Megafactory was designed to bring together in one location the different activities required to manufacture satellites. It houses cleanrooms and production areas equipped with cutting-edge technology, facilities dedicated to satellite testing, as well as offices.

Main structural works completed in record time

Construction of the Megafactory began in summer 2024. BESIX, together with its partner Galère, was responsible for the foundations, structural works, façades and finishing, as well as coordinating eight technical packages to ensure they were properly integrated into the building. The initial stages involved excavation, the construction of deep foundations and the installation of the geothermal system. No fewer than 562 foundation piles were installed with support from Franki Foundations, a subsidiary of BESIX Group. In record time, the teams successfully completed all the building’s structural works and made it watertight.

Complex geometry and structure

The building’s ovoid shape required a high degree of precision during construction, in addition to a complex hybrid structure combining concrete and steel. Precast beams and columns were combined with in-situ concrete cores to meet the building’s geometric constraints and support heavy equipment. Constructing the curved façades, with their steel framework and insulated panels, presented a further challenge. Each component was modelled in BIM to optimise coordination between the various project teams and ensure proper integration.

Specialised facilities for satellite testing

Ectro’s Megafactory (formerly Aerospacelab) includes facilities specifically designed to test satellites before they enter service. In particular, the building houses shakers, equipment capable of replicating the intense vibrations to which satellites will be subjected.

One of the project’s major technical challenges was constructing the shaker bases: five concrete blocks, each measuring around 70 m³, mounted on springs and capable of supporting test equipment subjected to extreme vibrations while isolating the rest of the building. Built after the main structure, these elements required exceptionally dense and complex reinforcement, as well as highly specialised formwork and construction methods.
Alexandre Duthoit
Projetct Manager , BESIX

Sustainability built into the building

The Megafactory incorporates several solutions to reduce its energy requirements: nearly 700 rooftop solar panels, a geothermal system and a district heating network. Its architecture, combined with a perforated metal façade, also helps regulate the building’s temperature.

Expertise for complex industrial projects

For BESIX, this project demonstrates its expertise in constructing complex, highly specialised industrial buildings for sectors of strategic importance to Europe.