
State road 318 is a crucial axis for east-west connections in Italy. Leaving Perugia, in the direction of Ancona, it passes through the beautiful hilly countryside of Umbria, including that of the Valfabbrica municipality, after which the project is named. The contract awarded by ANAS S.p.A., the company that manages the Italian public road network, includes the construction of an impressive variety of civil works, in particular the tunnels of Casacastalda and Picchiarella, which are 1,545 meters and 874 meters long respectively, the 130-metre Tre Vescovi viaduct and the 60-metre Calvario bridge. These will add two lanes of traffic to the existing road.
“On 31 January, we installed the steel span of the Calvario Bridge. It is a 246-tonne steel structure, which we first assembled next to the future bridge. The operation consisted of lifting it, which we did with two 500- and 800-ton cranes, and placing it in its final position,” explains Hervé Jourquin, BESIX's deputy project manager on the site. Because of the presence of electricity poles, which required one of the cranes to be moved during the operation, the installation had to be carried out in two stages, an additional challenge that was brilliantly met by the site teams. “The next step will be to install the concrete pre-slabs and pour the reinforced concrete deck structure. From the end of March, the site machinery will be able to use it, which will facilitate traffic on site,” continues Hervé. The asphalt will not be laid until the end of the work, in two years' time.
Before the end of the year, the span of the Tre Vescovi viaduct will also be installed. The method here will be different, as the span will be pushed instead of being lifted after being assembled at one end.
“We work 6 days a week, 24 hours a day. In all, with the shifts that this involves, we will have 80 people working on this tunnel, and between 120 and 150 with the Picchiarella tunnel, which will be built using the same method.” The excavation of the second tunnel is expected to start in mid-2022. In all, the two tunnels will require 8,240 tons of steel just for the consolidation of the excavation operations and a further 4,060 tons for the reinforcement.
)
)
)