United Arab Emirates, Dubai

Deep Tunnel Storm Water System

A groundbreaking tunnel for sustainable living in Dubai
The project, awarded to the Six Construct – PORR joint venture, consisted of a 10 km tunnel of 11.05 m boring diameter at a depth of 30 to 45 m. On top of that, four deep shafts (40 to 45 m deep) were constructed to connect the connection chambers, in which groundwater and storm water is collected and conveyed. In total, the system drains almost 40% of the entire urban area of Dubai, a total of 380 km².

Project details

Project nameDeep Tunnel Storm Water System
LocationDubai United Arab Emirates
Building period2017 - 2021
CategoryTunnels, Sewerage
Stakeholder(s)Six Construct
Contract typeDesign & Build
ClientDubai Municipality
Total Value Dollar$ 354000000