The main sequences of works were:
- Production of rock from the quarry
- Production of precast accropodes
- Removal by a cutter suction dredger of the silt material underneath the breakwater
The works BESIX carried out consisted of the design and construction of an off-shore breakwater of 2,300 m and an unloading jetty for LNG vessels. The piling works for the jetty were done from an 800 t capacity jack-up platform supporting one 100 t and one 200 t crawler crane.
The main sequences of works were:
The works at the jetty included:
Project name
Dabhol LNG Terminal
Area(s) of expertise
Jetties, Breakwaters
Contract type
Build
Location
Dabhol, India
Stakeholder(s)
BESIX
Client
Dabhol Power Company, India with ENRON Engineering Co. as developer (represented by Lingtec Constructors)
Building Period
1998 - 2001
Total value
$ 125 million